STC-DUBA REHAB PROJECT
- Client : STC
- Main Contractor : ACES
- Consultant : STC
- Location : DUBA
- Project : STC-DUBA REHAB PROJECT
- Project Duration : 3 MONTHS
- Project Cost : 0.7 MILLION
Scope of Work: mep & civil work.
Scope: civil works mechanical work-HVAC. Electrical works-low voltage &low current.
PHASE 2 ESKAN
- Client : DARUL RIYADH
- Main Contractor : SEDIARY ABDUL RAHMAN CONTRACTING.CO
- CONSULTANT: DARUL RIYADH
- Location : RIYADH
- Project : DARUL-RIYADH HQ BUILDING
- Project Duration : 3 MONTHS
- PROJECT COST : 205 MILLION
Scope of Work: mep work.
Renovation of all mep service for 8 floor building.